Consbec Mining + Construction
The finished spillway channel cut through rock at Caribou Mine, with water running through it toward the pond
Surface Mining

Tailings, dams & spillways

Caribou Mine — Tailings Dam Raise

Near Bathurst, New BrunswickDec 2025 – Feb 2026Completed

Blasts, every one monitored
30
Highest vibration recorded
9.2 mm/s
Of the 25 mm/s limit, at its peak
37%
Lowest frequency — none below it
20 Hz

The Work

New spillways cut into rock beside a tailings dam and its concrete spillway — 30 blasts under a 25 mm/s limit at the dam, every one independently monitored, the highest reading 37% of the limit.

The Caribou Mine, about 50 km west of Bathurst, is in care and maintenance — but its tailings facility still has to be raised. That meant cutting new service and auxiliary spillways into rock right beside the existing Main Dam and its concrete spillway: structures that cannot be put at risk.

The specification left little room. A 25 mm/s vibration limit within a metre of the dam and spillway structures, no subdrill anywhere near concrete, full blast mats on every shot, and pre-split final walls so the new concrete would sit on sound rock. The plan called for test blasts before production.

The rock was shallow, too, and without subdrill a cartridge-loaded hole tends to leave a hump of rock standing at the toe. So we brought bulk emulsion onto the job with our 1,800 kg mini pumper. Pumped emulsion fills the hole wall to wall and delivers full energy right down at the toe. The shots pulled good floor with no subdrill at all — something packaged product, in the same pattern and hole size, would not have done.

Every one of the 30 blasts was monitored by an independent consultant, with seismographs at the toe and the crest of the dam. The highest reading of the program was 9.2 mm/s — 37% of the limit. Just as important for an earth dam: not one of 171 frequency readings fell below 20 Hz. Low-frequency vibration is what dams are most sensitive to.

That record now does a second job. Regressed into a site-specific attenuation model, it is the design basis for the spillway work at Heath Steele.

Vibration Record

Every blast, against the limit

30 blasts. The highest reading was 9.2 mm/s — 37% of the 25 mm/s limit at the Main Dam. No blast exceeded it.

0102030mm/sLimit 25 mm/sPeak 9.2151015202530
Peak vector sum (mm/s), highest of the stations monitoring each blast. Limit: Allowable PPV within 1 m of the dam and spillway structures, 25 mm/s. Independent third-party seismograph monitoring, two stations per blast. 12 Dec 2025 to 8 Feb 2026.
View as table
BlastVibration (mm/s)Detail
Blast 1 — 12 Dec 20251.7773 Hz · Existing Spillway
Blast 2 — 15 Dec 20254.2545 Hz · Toe of Main Dam
Blast 3 — 16 Dec 20257.141 Hz · Toe of Main Dam
Blast 4 — 17 Dec 20254.2539.4 Hz · Toe of Main Dam
Blast 5 — 18 Dec 20256.6750 Hz · Toe of Main Dam
Blast 6 — 9 Jan 20268.9432.5 Hz · Toe of Main Dam
Blast 7 — 12 Jan 20268.1830 Hz · Toe of Main Dam
Blast 8 — 13 Jan 20267.5432 Hz · Toe of Main Dam
Blast 9 — 14 Jan 20266.3335.9 Hz · Toe of Main Dam
Blast 10 — 15 Jan 20265.7535.9 Hz · Toe of Main Dam
Blast 11 — 16 Jan 20265.2436.6 Hz · Toe of Main Dam
Blast 12 — 19 Jan 20268.4428.4 Hz · Toe of Main Dam
Blast 13 — 20 Jan 20269.1634.1 Hz · Toe of Main Dam
Blast 14 — 21 Jan 20262.2726 Hz · Crest of Main Dam
Blast 15 — 24 Jan 20266.8538 Hz · Toe of Main Dam
Blast 16 — 26 Jan 20267.4743 Hz · Toe of Main Dam
Blast 17 — 28 Jan 20266.9164 Hz · Toe of Main Dam
Blast 18 — 29 Jan 20263.9438 Hz · Mid-West of Main Dam
Blast 19 — 30 Jan 20267.3273 Hz · Mid-West of Main Dam
Blast 20 — 1 Feb 20266.5354 Hz · Mid-West of Main Dam
Blast 21 — 2 Feb 20267.3279 Hz · Mid-West of Main Dam
Blast 22 — 3 Feb 20265.0337 Hz · Crest of Main Dam (West Side)
Blast 23 — 4 Feb 20263.8839 Hz · Crest of Main Dam (West Side)
Blast 24 — 5 Feb 20262.9739 Hz · Crest of Main Dam (West Side)
Blast 25 — 6 Feb 20263.5832 Hz · Crest of Main Dam (West Side)
Blast 26 — 5 Feb 20263.3751 Hz · Crest of Main Dam (West Side)
Blast 27 — 7 Feb 20262.7251 Hz · Mid-West of Main Dam
Blast 28 — 8 Feb 20261.5937 Hz · Crest of Main Dam (West Side)
Blast 29 — 8 Feb 20261.8634 Hz · Crest of Main Dam (West Side)
Blast 30 — 8 Feb 20261.4547 Hz · Crest of Main Dam (West Side)

Bulk Emulsion

Loaded with our own emulsion

Shallow rock, a concrete spillway next door and no subdrill allowed. We brought our 1,800 kg mini pumper and loaded the production holes with bulk emulsion. Pumped emulsion fills the hole wall to wall and puts full energy right down at the toe, so the shots still pulled good floor without subdrill. Packaged product in the same pattern and hole size would not have.

How we use emulsion
A Consbec mini pumper truck carrying a bulk emulsion tote and pumping unit

Next Project

Heath Steele Mine — Auxiliary Spillway

A new auxiliary spillway cut through rock near two tailings dams, held to 25 mm/s at the dam — designed from measured vibration data rather than textbook constants, and loaded with metered bulk emulsion.