Consbec Mining + Construction
Surface Mining

Tailings, dams & spillways

Heath Steele Mine — Auxiliary Spillway

Wayerton, New Brunswick2026 – ongoingActive

Blasts in September 2026
15
Highest vibration at the dam
4.3 mm/s
Of the 25 mm/s limit, at its peak
17%
Lowest dominant frequency
32 Hz

The Work

A new auxiliary spillway cut through rock near two tailings dams, held to 25 mm/s at the dam — designed from measured vibration data rather than textbook constants, and loaded with metered bulk emulsion.

Heath Steele, near Wayerton, is a closed mine with a tailings facility that still has to be maintained. The new auxiliary spillway is cut through rock near both the Main Dam and the Internal Dam, with a hard limit of 25 mm/s within a metre of either.

The usual way to design for a limit like that is a textbook attenuation formula. We didn’t. The blast designs use constants regressed from the measured vibration of 30 monitored blasts at the Caribou tailings dam raise — a directly comparable New Brunswick site — and they design to the 95% upper prediction bound of that data, not its average. The blasting plan was independently reviewed before work began, and a trigger-action plan sets out exactly what happens at 15, 20 and 25 mm/s.

Production holes are loaded with bulk emulsion from our 1,800 kg mini pumper, metered hole by hole. A fully coupled column with a known mass in every hole is what makes charge per delay — and therefore vibration — predictable. It is also what pulls the floor: the rock is shallow and there is no subdrill near the concrete, and pumped emulsion puts full energy at the toe of the hole where packaged product, in the same pattern and hole size, would leave it standing.

Through the first 15 blasts, the highest reading at the dam was 4.3 mm/s, and every blast stayed in the normal operating band.

Vibration Record

Every blast, against the limit

15 blasts. The highest reading was 4.3 mm/s — 17% of the 25 mm/s limit at the Main Dam. No blast exceeded it.

0102030mm/sLimit 25 mm/sPeak 4.3123456789101112131415
Measured PPV (mm/s), greatest single-component peak at the Main Dam. Limit: Absolute PPV limit within 1 m of the Main Dam and Internal Dam, 25 mm/s. Every blast monitored; design to a 95% upper prediction bound, with a trigger-action response plan. 2 Sep 2026 to 21 Sep 2026. Outline: seismograph did not trigger (below its threshold).
View as table
BlastVibration (mm/s)Detail
Blast 1 — 2 Sep 20261.2751 Hz
Blast 2 — 3 Sep 20261.0257 Hz
Blast 3 — 3 Sep 20260.8939 Hz
Blast 4 — 4 Sep 20262.1632 Hz
Blast 5 — 7 Sep 20261.7839 Hz
Blast 6 — 8 Sep 20263.05
Blast 7 — 8 Sep 20263.05
Blast 8 — 10 Sep 20261.5243 Hz
Blast 9 — 11 Sep 20261.9173 Hz
Blast 10 — 12 Sep 20263.4357 Hz
Blast 11 — 14 Sep 20264.3243 Hz
Blast 12 — 16 Sep 20261.02
Blast 13 — 18 Sep 20261.52
Blast 14 — 20 Sep 2026< 0.5 (no trigger)
Blast 15 — 21 Sep 2026< 0.5 (no trigger)

Bulk Emulsion

Loaded with our own emulsion

Shallow rock, concrete close by and no subdrill allowed. We brought our 1,800 kg mini pumper and loaded every production hole with bulk emulsion. Pumped emulsion fills the hole wall to wall and puts full energy right down at the toe, so the shots still pulled good floor without subdrill. Packaged product in the same pattern and hole size would not have.

How we use emulsion
A Consbec mini pumper truck carrying a bulk emulsion tote and pumping unit

Next Project

Highway 103 Twinning

Mass rock excavation for the twinning of Highway 103 at Chester — 216 blasts since September 2025, loaded with bulk emulsion, beside an open highway and under a 12.5 mm/s limit at the nearest structure.